Under construction

ORION IMPERIAMahaRERA P49600000043

by Mpoonam Developers LLP

732/1 , 732/3 , 732/4, Naroli, 396235

Dec 2030
Possession
19.9%
Built
0
Complaints
718
Units
High risk
  • Possession delayed ~5 yrs. Originally promised Jan 2026, now proposed Dec 2030 per the RERA filing.

Official RERA facts

Registration
P49600000043
Status
Ongoing
Stage
Certificate Signed
Possession
December 2030originally January 2026
Construction
19.9% complete
Units sold
309 of 718

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)70%
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Street Lightingdone
Community Buildingsdone
Treatment And Disposal Of Sewage And Sullage Water75%
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone
Aggregate area of recreational Open Spacedone
Open Parkingdone

Building & registration

RERA registered
Dec 2017
Floors
32
Unit mix
632 res ยท 86 comm
Architect
Design Work Group

Buyer community

Connect with other buyers and owners of ORION IMPERIA โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching ORION IMPERIA. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.