Under construction

RAKA PARKMahaRERA P49800009342

by ADINATH INFRASTRUCTURE

SURVEY NO 150/2 PLOT NO 20 WALWADI SHIVAR PIN424005, Walwadi (CT), 424005

Dec 2020
Possession
65.9%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~2 yrs. Originally promised Aug 2018, now proposed Dec 2020 per the RERA filing.
  • Possession date passed. The proposed possession date (Dec 2020) has passed with construction at 65.9%.

Official RERA facts

Registration
P49800009342
Status
Ongoing
Stage
Certificate Signed
Possession
December 2020originally August 2018
Construction
65.9% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Sewerage (Chamber, Lines, Septic Tank , STP)done
Landscaping & Tree Plantingdone
Street Lightingdone
Water conservation /Rain water harvestingdone
Open Parkingdone

Building & registration

RERA registered
Aug 2017
Floors
5

Buyer community

Connect with other buyers and owners of RAKA PARK โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching RAKA PARK. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.