Under construction

Suman ApartmentMahaRERA P49800034964

by Siddhivinayak Engineer and Contractors

Plot No.31, C.T.S. No 8292, S.No. 37/1, Deopur, Dhule, Deopur, Dhule, 424002

Jul 2027
Possession
40%
Built
0
Complaints
21
Units
High risk
  • Possession delayed ~4 yrs. Originally promised Jun 2023, now proposed Jul 2027 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jul 2027 per the RERA filing.

Official RERA facts

Registration
P49800034964
Status
New
Stage
Certificate Signed
Possession
July 2027originally June 2023
Construction
40% complete
Units sold
0 of 21

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Apr 2022
Floors
6
Unit mix
21 res ยท 0 comm
Architect
Bupesh R Patil

Buyer community

Connect with other buyers and owners of Suman Apartment โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Suman Apartment. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.