Under construction

ADITYA HEIGHTSMahaRERA P49900025748

by MAYURI MUKUND BILDIKAR

PLOT NO 58 S NO 81/1A/1, 81/1B/2, VIVEKANAND NAGAR, 424201

Mar 2027
Possession
44.5%
Built
0
Complaints
21
Units
High risk
  • Possession delayed ~5 yrs. Originally promised Jun 2022, now proposed Mar 2027 per the RERA filing.
  • Behind schedule. Possession is due Mar 2027 but construction is only at 44.5%.

Official RERA facts

Registration
P49900025748
Status
New
Stage
Certificate Signed
Possession
March 2027originally June 2022
Construction
44.5% complete
Units sold
13 of 21

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Jul 2020
Floors
6
Unit mix
16 res ยท 5 comm
Architect
Rizani Associates

Buyer community

Connect with other buyers and owners of ADITYA HEIGHTS โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching ADITYA HEIGHTS. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.