PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

MARATHA COMMERCIAL COMPLEXMahaRERA P50200051851

by DHANLAKSHMI BUILDERS AND DEVELOPERS

Plot No. 1 S.N. 323/1 & 324/1, RISOD NAKA, 444505

Aug 2024
Possession
81.8%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Aug 2024) has passed with construction at 81.8%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Aug 2024 per the RERA filing.

Official RERA facts

Registration
P50200051851
Status
New
Stage
Certificate Signed
Possession
August 2024
Construction
81.8% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsdone
Landscaping & Tree Plantingnot started
Street Lightingnot started
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving station80%
Open Parkingnot started

Building & registration

RERA registered
Jul 2023
Floors
2

Buyer community

Connect with other buyers and owners of MARATHA COMMERCIAL COMPLEX โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching MARATHA COMMERCIAL COMPLEX. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.