PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

VITTHALARPAN RESIDENCY-BMahaRERA P50300004073

by DHANRAJ HARICHAND KHANDELWAL

PLOT NO 5-A,5-B,6,7, Amravati (M Corp.), 444607

Jan 2022
Possession
25.3%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~1 yr. Originally promised Aug 2020, now proposed Jan 2022 per the RERA filing.
  • Possession date passed. The proposed possession date (Jan 2022) has passed with construction at 25.3%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jan 2022 per the RERA filing.

Official RERA facts

Registration
P50300004073
Status
Ongoing
Stage
Certificate Signed
Possession
January 2022originally August 2020
Construction
25.3% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supply10%
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Aug 2017
Floors
7

Buyer community

Connect with other buyers and owners of VITTHALARPAN RESIDENCY-B โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching VITTHALARPAN RESIDENCY-B. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.