Under construction

SHIVANAND HEIGHTSMahaRERA P50300005800

by SHIVANAND INFRASTRUCTURE

27, Amravati (M Corp.), 444606

Feb 2023
Possession
100%
Built
0
Complaints
0
Units
Caution
  • Possession delayed ~2 yrs. Originally promised Aug 2020, now proposed Feb 2023 per the RERA filing.

Official RERA facts

Registration
P50300005800
Status
Ongoing
Stage
Certificate Signed
Possession
February 2023originally August 2020
Construction
100% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Treatment And Disposal Of Sewage And Sullage Waterdone
Water conservation /Rain water harvestingdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone

Building & registration

RERA registered
Aug 2017
Floors
8

Buyer community

Connect with other buyers and owners of SHIVANAND HEIGHTS โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SHIVANAND HEIGHTS. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.