Under construction

ORANGE COUNTYMahaRERA P50300011513

by DNYANESHWAR NAMDEVRAO WANKHADE

4215/ 42/5/ 7B,8A,8B, AMRAVATI, 444604

Oct 2020
Possession
57.5%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~2 yrs. Originally promised Dec 2018, now proposed Oct 2020 per the RERA filing.
  • Possession date passed. The proposed possession date (Oct 2020) has passed with construction at 57.5%.

Official RERA facts

Registration
P50300011513
Status
Ongoing
Stage
Certificate Signed
Possession
October 2020originally December 2018
Construction
57.5% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Water conservation /Rain water harvesting70%
Open Parkingdone

Building & registration

RERA registered
Aug 2017
Floors
4

Buyer community

Connect with other buyers and owners of ORANGE COUNTY โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching ORANGE COUNTY. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.