Construction of 674 EWS T/s 409 MIG T/s 104 HIG T/s under PMAY at Akoli Amravati / EWS and MIGMahaRERA P50300015120

by Amravati Housing And Area Development Board Amravati

47,57,58, Akoli, 444606

Dec 2022
Possession
89.1%
Built
0
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Dec 2022) has passed with construction at 89.1%.

Official RERA facts

Registration
P50300015120
Status
New
Stage
Certificate Signed
Possession
December 2022
Construction
89.1% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)95%
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Street Lightingdone
Treatment And Disposal Of Sewage And Sullage Water95%
Solid Waste Management And Disposaldone
Water conservation /Rain water harvestingdone
Electrical meter room, sub-station, receiving stationdone
Aggregate area of recreational Open Spacedone
Open Parkingdone

Building & registration

RERA registered
Jan 2018
Floors
5

Buyer community

Connect with other buyers and owners of Construction of 674 EWS T/s 409 MIG T/s 104 HIG T/s under PMAY at Akoli Amravati / EWS and MIG โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Construction of 674 EWS T/s 409 MIG T/s 104 HIG T/s under PMAY at Akoli Amravati / EWS and MIG. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.