Under construction

AYUR MALLMahaRERA P50300016040

by K. K. INFRASTRUCTURE

59/3, AMRAVATI, 444601

Jan 2022
Possession
0%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Jan 2022) has passed with construction at 0%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jan 2022 per the RERA filing.

Official RERA facts

Registration
P50300016040
Status
New
Stage
Certificate Signed
Possession
January 2022
Construction
0% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Internal Roads & Footpathsnot started
Internal Roads & Footpathsnot started
Internal Roads & Footpathsnot started
Internal Roads & Footpathsnot started
Internal Roads & Footpathsnot started
Water Supplynot started
Water Supplynot started
Water Supplynot started
Water Supplynot started
Water Supplynot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Storm Water Drainsnot started
Storm Water Drainsnot started
Storm Water Drainsnot started
Storm Water Drainsnot started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Landscaping & Tree Plantingnot started
Landscaping & Tree Plantingnot started
Landscaping & Tree Plantingnot started
Landscaping & Tree Plantingnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Street Lightingnot started
Street Lightingnot started
Street Lightingnot started
Street Lightingnot started
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Water conservation /Rain water harvestingnot started
Water conservation /Rain water harvestingnot started
Water conservation /Rain water harvestingnot started
Water conservation /Rain water harvestingnot started
Water conservation /Rain water harvestingnot started
Water conservation /Rain water harvestingnot started

Building & registration

RERA registered
Apr 2018
Floors
4

Buyer community

Connect with other buyers and owners of AYUR MALL โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching AYUR MALL. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.