PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

Dreamz PrideMahaRERA P50300020591

by Dreamz Infravision

15/2, 15/2-A, Badnera Road, 444605

May 2023
Possession
75.5%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (May 2023) has passed with construction at 75.5%.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due May 2023 per the RERA filing.

Official RERA facts

Registration
P50300020591
Status
New
Stage
Certificate Signed
Possession
May 2023
Construction
75.5% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Community Buildingsnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Apr 2019
Floors
14

Buyer community

Connect with other buyers and owners of Dreamz Pride โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Dreamz Pride. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.