Sept 2026
Possession
56.6%
Built
0
Complaints
197
Units
High risk
  • Possession delayed ~2 yrs. Originally promised Mar 2025, now proposed Sept 2026 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Sept 2026 per the RERA filing.

Official RERA facts

Registration
P50300031314
Status
New
Stage
Certificate Signed
Possession
September 2026originally March 2025
Construction
56.6% complete
Units sold
128 of 197

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths55%
Water Supply55%
Sewerage (Chamber, Lines, Septic Tank , STP)20%
Landscaping & Tree Plantingnot started
Street Lighting20%
Community Buildings40%
Treatment And Disposal Of Sewage And Sullage Waternot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirements40%
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Oct 2021
Floors
14
Unit mix
135 res ยท 62 comm

Buyer community

Connect with other buyers and owners of Vivanta Infinity Private Limited โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Vivanta Infinity Private Limited. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.