PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

SAIKRUPAMahaRERA P50300032125

by Saidutta Developers

3/1, MOUJE-SATURNA, 444607

Dec 2024
Possession
69.1%
Built
0
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Dec 2024) has passed with construction at 69.1%.

Official RERA facts

Registration
P50300032125
Status
New
Stage
Certificate Signed
Possession
December 2024
Construction
69.1% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths90%
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)90%
Storm Water Drainsnot started
Landscaping & Tree Planting90%
Street Lighting80%
Community Buildingsdone
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving station90%
Aggregate area of recreational Open Spacedone

Building & registration

RERA registered
Dec 2021
Floors
3

Buyer community

Connect with other buyers and owners of SAIKRUPA โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SAIKRUPA. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.