PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

SHRI SAI GAJANAN ENCLAVE IIMahaRERA P50300046007

by JEET SHUTAKSHI BUILDERS

36/37A/37B/38A/38B, NEAR JAWARKAR LAWN, 444604

Mar 2027
Possession
34.5%
Built
1
Complaints
0
Units
Caution
  • Behind schedule. Possession is due Mar 2027 but construction is only at 34.5%.

Official RERA facts

Registration
P50300046007
Status
New
Stage
Certificate Signed
Possession
March 2027
Construction
34.5% complete
Units sold
0 of 0

RERA complaint record1 record

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Open Parkingnot started

Building & registration

RERA registered
Jun 2022
Floors
9

Buyer community

Connect with other buyers and owners of SHRI SAI GAJANAN ENCLAVE II โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SHRI SAI GAJANAN ENCLAVE II. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.