MAJESTIC RESIDENCY

MahaRERA P50400050776Clean record

by SKYLINE INFRA

PLOT NO 241/2, CTS NO.241/2 SHEET NO 54, PALAKWADI WARDHA, 442001

Official record
Sept 2026
Possession
81.8%
Built
0
Complaints
16
Units
Clean record

No delays, complaints or enforcement actions in the official disclosures we track.

Official RERA facts

Registration
P50400050776
Status
New
Stage
Certificate Signed
Possession
September 2026originally December 2025
Construction
81.8% complete
Units sold
12 of 16

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 24 Jul 2026).

Landowner

SKYLINE INFRA

Possession extension history

  • EA03052620816Revised to September 2026

    We, MARIGOLD REALITY (Promoter), through our Partner and Authorized Signatory MR. MUSTAFA SAJJAD SAIFEE, of the real estate project “MAJESTIC RESIDENCY”, bearing MahaRERA Registration No. P50400050776, respectfully submit this application seeking an extension of Nine (9) months i.e., up to 30/09/2026 for the completion of the project. The originally declared project completion date under MahaRERA was 31/12/2025. However, we have received the Occupation Certificate (OC) on 09/01/2026. The project experienced minor delays due to: • Delays in obtaining certain statutory approvals and completing procedural formalities • Temporary interruptions in construction activities due to shortage of labour • Occasional delays in the supply of construction materials • Coordination challenges with utility departments such as electricity and water authorities These factors, though not substantial individually, cumulatively led to a slight delay in achieving the final completion milestone. We further clarify that this extension is being sought solely for the purpose of submission of the Occupation Certificate on the MahaRERA portal and for obtaining formal acceptance/recording of the same by the Hon’ble Authority. The project is already completed, and the OC has been duly obtained. We humbly request the Authority to grant the said extension up to 30/09/2026 and kindly condone the delay, considering that the project has now been completed and the Occupation Certificate has already been obtained. We assure you of our continued compliance with all applicable rules and regulations under the Real Estate (Regulation and Development) Act.

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Water conservation /Rain water harvestingdone
Electrical meter room, sub-station, receiving stationdone

Building & registration

RERA registered
May 2023
Floors
5
Unit mix
16 res · 0 comm
Plot / CTS / survey no.
PLOT NO 241/2, CTS NO.241/2 SHEET NO 54
Planning authority
Wardha Municipal Council
Approved layout land
769 sq.m
Land for this registration
769 sq.m
Permissible built-up area
1,353.44 sq.m
Registered office
SKYLINE INFRA
Plot boundaries
North
NAGAR PARISHAD LANE
South
NAGAR PARISHAD ROAD AND HOUSE OF MR PISE
East
HOUSE OF MR SALUNKE
West
NAGAR PARISHAD LANE AND OPEN SPACE
Parking
5 four-wheeler25 two-wheeler

Project bank account

The RERA-designated account this project's payments should go to — verify before wiring any money.

  • AU SMALL FINANCE BANK LIMITED — 2889
    IFSC AUBL0002371
    GANDHI NAGAR, WARDHA

Commencement Certificate documents

  • BUILDING DEVELOPMENT PERMISSION.pdf

Buyer community

Connect with other buyers and owners of MAJESTIC RESIDENCY — compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet — start one and connect with the next buyer researching MAJESTIC RESIDENCY. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.