HARIHAR NAGAR ZARI PHASE - IMahaRERA P50500000975

by HARIHAR INFRASTRUCTURE DEVELOPMENT CORPORATION LIMITED

68/2, 68/3, 68/4, 68/5, Nagpur (rural), 441108

Sept 2033
Possession
0%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~12 yrs. Originally promised Oct 2021, now proposed Sept 2033 per the RERA filing.

Official RERA facts

Registration
P50500000975
Status
Ongoing
Stage
Certificate Signed
Possession
September 2033originally October 2021
Construction
0% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Street Lightingdone
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvesting70%
Electrical meter room, sub-station, receiving stationdone

Building & registration

RERA registered
Jul 2017
Floors
1
Architect
Anant Shrikant Raole

Buyer community

Connect with other buyers and owners of HARIHAR NAGAR ZARI PHASE - I โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching HARIHAR NAGAR ZARI PHASE - I. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.