Under construction
Vista 3BMahaRERA P50500003509
by Luxora Infrastructure Private Limited
Kh No.97/1 Pt 97/2 Pt 97/3 pt 97/4 pt, Mauza, 440034
Dec 2026
Possession
14.3%
Built
1
Complaints
84
Units
High risk
- Possession delayed ~5 yrs. Originally promised Dec 2021, now proposed Dec 2026 per the RERA filing.
- Behind schedule. Possession is due Dec 2026 but construction is only at 14.3%.
Official RERA facts
- Registration
- P50500003509
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- December 2026originally December 2021
- Construction
- 14.3% complete
- Units sold
- 4 of 84
RERA complaint record1 record
- ComplaintCC00400000001002417 Jan 2018shivani Tomar vs Luxora Infrastructure Private Limited10024 Shivani Tomar Vs Luxora Infrastructure Pvt Ltd.pdf on MahaRERA
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpaths62%
Water Supply35%
Sewerage (Chamber, Lines, Septic Tank , STP)67%
Storm Water Drains67%
Landscaping & Tree Planting80%
Street Lighting10%
Community Buildings50%
Treatment And Disposal Of Sewage And Sullage Waterdone
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving station37%
Open Parkingnot started
Building & registration
- RERA registered
- Aug 2017
- Floors
- 8
- Unit mix
- 84 res ยท 0 comm
- Architect
- Studio Eleven
Buyer community
Connect with other buyers and owners of Vista 3B โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching Vista 3B. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.