Park Mansion 48MahaRERA P50500004854
by Luxora Infrastructure Private Limited
Kh. No.96/1/2/3/4 part 97/1/2/3/4 part, Mauza, 440034
Dec 2028
Possession
22.1%
Built
0
Complaints
1
Units
High risk
- Possession delayed ~10 yrs. Originally promised Dec 2018, now proposed Dec 2028 per the RERA filing.
Official RERA facts
- Registration
- P50500004854
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- December 2028originally December 2018
- Construction
- 22.1% complete
- Units sold
- 1 of 1
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 23 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpaths62%
Water Supply35%
Sewerage (Chamber, Lines, Septic Tank , STP)67%
Storm Water Drains67%
Landscaping & Tree Planting80%
Street Lighting10%
Community Buildings50%
Treatment And Disposal Of Sewage And Sullage Waterdone
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving station37%
Building & registration
- RERA registered
- Aug 2017
- Floors
- 2
- Unit mix
- 1 res ยท 0 comm
- Architect
- Studio Eleven
Buyer community
Connect with other buyers and owners of Park Mansion 48 โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching Park Mansion 48. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.