Under construction

Shiv Brighton Phase IMahaRERA P50500006203

by Om Shivam Buildcon Private Limited

Plot No 1 Kh No 59 / 3 Mouza Panjri, Panjari farm, 441108

Jan 2021
Possession
90.9%
Built
0
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Jan 2021) has passed with construction at 90.9%.
GoregaonUpper-mid

Film City flank with large integrated townships on both flanks.

Growth drivers:
Oberoi/NESCO belt, Metro 7, Western Express Highway offices.
Who buys here:
Upgraders wanting township amenities without Powai prices.

PropPin area guide โ€” editorial, not a RERA disclosure.

Official RERA facts

Registration
P50500006203
Status
Ongoing
Stage
Certificate Signed
Possession
January 2021
Construction
90.9% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Street Lightingdone
Community Buildingsdone
Treatment And Disposal Of Sewage And Sullage Waterdone
Solid Waste Management And Disposaldone
Water conservation /Rain water harvestingdone
Energy managemcntdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone
Aggregate area of recreational Open Spacedone

Building & registration

RERA registered
Aug 2017
Floors
7

Buyer community

Connect with other buyers and owners of Shiv Brighton Phase I โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Shiv Brighton Phase I. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.