Bloomdale Building 09MahaRERA P50500006483
by Mahindra Bebanco Developers Limited
17 Part 18 Part 19 Part 26 Part 27 Part 28 29 Part 30 Part 31 Part 35 Part 36 Part 39 Part Governmen, Khapri, 441108
- Possession delayed ~2 yrs. Originally promised Mar 2019, now proposed Sept 2020 per the RERA filing.
- Possession date passed. The proposed possession date (Sept 2020) has passed with construction at 90.9%.
Official RERA facts
- Registration
- P50500006483
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- September 2020originally March 2019
- Construction
- 90.9% complete
- Units sold
- 0 of 0
RERA complaint record2 records
- ComplaintCC00400000003020815 Dec 2020DILIPKUMAR JAGANNATH GAJBHIYE vs MAHINDRA BLOOMDALE DEVELOPERS LIMITEDFO30208.pdf on MahaRERA
- ComplaintCC0040000000101013 Jun 2019Mr. Syed Waqar Abbas Naqvi vs Mahindra Bebanco Developers Limitedsayed waqar abbs naqvi20112019100230.pdf on MahaRERA
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- Aug 2017
- Floors
- 9
Buyer community
Connect with other buyers and owners of Bloomdale Building 09 โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching Bloomdale Building 09. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.