PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

AMANS MANNATMahaRERA P50500008476

by GREEN CITY BUILDERS

1045, Nagpur (M Corp.), 440013

Mar 2027
Possession
75.5%
Built
0
Complaints
78
Units
High risk
  • Possession delayed ~6 yrs. Originally promised Apr 2021, now proposed Mar 2027 per the RERA filing.

Official RERA facts

Registration
P50500008476
Status
Ongoing
Stage
Certificate Signed
Possession
March 2027originally April 2021
Construction
75.5% complete
Units sold
49 of 78

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths45%
Water Supply15%
Sewerage (Chamber, Lines, Septic Tank , STP)15%
Street Lighting40%
Fire protection and fire safety requirements35%
Electrical meter room, sub-station, receiving station15%
Aggregate area of recreational Open Space50%
Open Parking60%

Building & registration

RERA registered
Aug 2017
Floors
15
Unit mix
78 res ยท 0 comm
Architect
RAJIV CHOUDHARY

Buyer community

Connect with other buyers and owners of AMANS MANNAT โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching AMANS MANNAT. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.