Under construction

Park House HolisticMahaRERA P50500011398

by Luxora Infrastructure Private Limited

Kh. No. 97/1/2/3/4 part and 82 pt, Mauza, 440034

Dec 2026
Possession
โ€”
Built
0
Complaints
31
Units
High risk
  • Possession delayed ~7 yrs. Originally promised Dec 2019, now proposed Dec 2026 per the RERA filing.

Official RERA facts

Registration
P50500011398
Status
Ongoing
Stage
Certificate Signed
Possession
December 2026originally December 2019
Construction
โ€”
Units sold
12 of 31

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths62%
Water Supply35%
Sewerage (Chamber, Lines, Septic Tank , STP)67%
Storm Water Drains67%
Landscaping & Tree Planting80%
Street Lighting10%
Community Buildings50%
Treatment And Disposal Of Sewage And Sullage Waterdone
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving station37%
Open Parkingnot started

Building & registration

RERA registered
Aug 2017
Floors
2
Unit mix
16 res ยท 0 comm
Architect
Studio Eleven

Buyer community

Connect with other buyers and owners of Park House Holistic โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Park House Holistic. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.