PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

SpringfieldMahaRERA P50500013193

by Luxora Infrastructure Private Limited

Kh No 75/1/3/4 , Kh No 74, Mauza, 440034

Mar 2026
Possession
โ€”
Built
1
Complaints
143
Units
High risk
  • Possession delayed ~6 yrs. Originally promised Sept 2019, now proposed Mar 2026 per the RERA filing.
  • Promised amenities not started. Clubhouse is at 0% build with possession due Mar 2026 per the RERA filing.

Official RERA facts

Registration
P50500013193
Status
New
Stage
Certificate Signed
Possession
March 2026originally September 2019
Construction
โ€”
Units sold
134 of 143

RERA complaint record1 record

  • ComplaintCC1250014115 Jan 2025
    Payal Arvind Bagade vs Luxora Infrastructure Private Limited

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Planting80%
Street Lighting50%
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Waterdone
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationdone
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Sept 2017
Architect
Studio Eleven

Buyer community

Connect with other buyers and owners of Springfield โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Springfield. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.