Under construction

LAVA 7 ESTATEMahaRERA P50500015613

by FAIR HOMES INFRAVENTURES PRIVATE LIMITED NAGPUR

18/3, MOUZA-LAVA, 440023

Dec 2028
Possession
60.4%
Built
1
Complaints
206
Units
High risk
  • Possession delayed ~6 yrs. Originally promised Apr 2023, now proposed Dec 2028 per the RERA filing.

Official RERA facts

Registration
P50500015613
Status
New
Stage
Certificate Signed
Possession
December 2028originally April 2023
Construction
60.4% complete
Units sold
122 of 206

RERA complaint record1 record

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths96%
Water Supply87%
Sewerage (Chamber, Lines, Septic Tank , STP)91%
Storm Water Drains89%
Landscaping & Tree Planting80%
Street Lighting85%
Water conservation /Rain water harvesting75%
Fire protection and fire safety requirements85%
Electrical meter room, sub-station, receiving station84%
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Mar 2018
Floors
8
Unit mix
191 res ยท 15 comm
Architect
LOKESH KADU

Buyer community

Connect with other buyers and owners of LAVA 7 ESTATE โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching LAVA 7 ESTATE. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.