Under construction

RAJATBHOOMI - 2

MahaRERA P50500017735High risk

by TIRUPATI DEVELOPERS

KH NO 72, NEAR JAMTHA STADIUM, 441108

Official record
Sept 2025
Possession
โ€”
Built
0
Complaints
9
Units
High risk
  • Possession delayed ~6 yrs. Originally promised Dec 2019, now proposed Sept 2025 per the RERA filing.

Official RERA facts

Registration
P50500017735
Status
New
Stage
Certificate Signed
Possession
September 2025originally December 2019
Construction
โ€”
Units sold
8 of 9

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 24 Jul 2026).

Possession extension history

  • EXT50500003757Revised to December 2020

    DEVELOPMENT ACTIVITY IS PENDING DUE TO HEAVY RAIN FALL

  • EXT50500011165Revised to September 2025

    This project was approved and sanctioned by NIT (Nagpur Improvement Trust ). Later Govt. of Maharashtra instituted NMRDA ( Nagpur Metropolitan Region Development Authority) as a statutory body for development in the region in place of NIT. The project initially got delayed because we had to again approach NMRDA for approval and sanction. Due to the ongoing Corona pandemic, the sale of plots has slowed down considerably. As we are selling most of the plots on an installment basis of 36 months to our buyers, we are yet to receive the entire cost of our sale proceeds. Although we have completed about 90% of work on the site and have received RL( Release Letter ), which is equivalent to OC( Occupation Certificate )for 90% of our plots from NMRDA. But we presume that due to the ongoing pandemic situation, the sale of remaining plots and the subsequent recovery of sale proceeds on an installment basis may take about 45 months hereafter. Hence we humbly request the MahaRera authority to grant us an extension till 30th September 2025 and oblige.

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Water95%
Water conservation /Rain water harvestingdone
Electrical meter room, sub-station, receiving stationdone
Aggregate area of recreational Open Spacedone

Building & registration

RERA registered
Sept 2018
Architect
UMESH MORESHWAR LAMGE
Plot / CTS / survey no.
KH NO 72
Planning authority
NAGPUR METROPOLITAN REGION DEVELOPMENT AUTHORITY
Approved layout land
4,885.81 sq.m
Land for this registration
4,885.81 sq.m
Recreational open space
600.87 sq.m
Permissible built-up area
0 sq.m
Registered office
NKY TOWERS
Plot boundaries
North
ADJ KH NO 71
South
PROPOSED ROAD WIDENING
East
ADJ KH NO 71
West
ADJ KH NO 73

Buyer community

Connect with other buyers and owners of RAJATBHOOMI - 2 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching RAJATBHOOMI - 2. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.