PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

MAHARAJA RESIDENCYMahaRERA P50500017753

by SHARIQUE KHAN

46, Mouza - Gorewada, 440013

Dec 2022
Possession
89.1%
Built
0
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Dec 2022) has passed with construction at 89.1%.

Official RERA facts

Registration
P50500017753
Status
New
Stage
Certificate Signed
Possession
December 2022
Construction
89.1% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Planting80%
Water conservation /Rain water harvestingdone
Energy managemcntdone
Open Parkingdone

Building & registration

RERA registered
Sept 2018
Floors
5

Buyer community

Connect with other buyers and owners of MAHARAJA RESIDENCY โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching MAHARAJA RESIDENCY. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.