RAJATBHOOMI - 5MahaRERA P50500018095

by TIRUPATI DEVELOPERS

SURVEY NO 87/2, NEAR JAMTHA STADIUM, 441108

Sept 2025
Possession
โ€”
Built
0
Complaints
56
Units
High risk
  • Possession delayed ~6 yrs. Originally promised Dec 2019, now proposed Sept 2025 per the RERA filing.

Official RERA facts

Registration
P50500018095
Status
New
Stage
Certificate Signed
Possession
September 2025originally December 2019
Construction
โ€”
Units sold
56 of 56

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Waterdone
Water conservation /Rain water harvestingdone
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacedone

Building & registration

RERA registered
Oct 2018

Buyer community

Connect with other buyers and owners of RAJATBHOOMI - 5 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching RAJATBHOOMI - 5. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.