PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

Mahindra Bloomdale 4BMahaRERA P50500020254

by Mahindra Bebanco Developers Limited

17 part 18 part 19 part 26 part 27 part 28 29 part 30 part 31 part 35 part 36 part 39 part, MIHAN Khapari, 441108

May 2023
Possession
78.2%
Built
2
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (May 2023) has passed with construction at 78.2%.

Official RERA facts

Registration
P50500020254
Status
New
Stage
Certificate Signed
Possession
May 2023
Construction
78.2% complete
Units sold
0 of 0

RERA complaint record2 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths90%
Water Supply76%
Sewerage (Chamber, Lines, Septic Tank , STP)73%
Storm Water Drains81%
Landscaping & Tree Planting70%
Street Lighting81%
Community Buildingsdone
Water conservation /Rain water harvesting86%
Fire protection and fire safety requirements88%
Electrical meter room, sub-station, receiving station89%
Aggregate area of recreational Open Space61%
Open Parking65%
CCTV system in Common Area38%
Childrens play Areadone
Half Basket ball courtdone
Power Back through DGdone
Swimming pool,done
Tennis courtdone

Building & registration

RERA registered
Mar 2019
Floors
9

Buyer community

Connect with other buyers and owners of Mahindra Bloomdale 4B โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Mahindra Bloomdale 4B. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.