Raje Vir Bahadur Shah LayoutMahaRERA P50500021448

by Adityapratap Veerbahadur Shah

107, 108, 109, 110, Mahurzari, 441501

Dec 2027
Possession
โ€”
Built
0
Complaints
44
Units
High risk
  • Possession delayed ~4 yrs. Originally promised Dec 2023, now proposed Dec 2027 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2027 per the RERA filing.

Official RERA facts

Registration
P50500021448
Status
New
Stage
Certificate Signed
Possession
December 2027originally December 2023
Construction
โ€”
Units sold
16 of 44

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supply20%
Sewerage (Chamber, Lines, Septic Tank , STP)80%
Storm Water Drainsdone
Landscaping & Tree Plantingnot started
Street Lighting70%
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Space80%

Building & registration

RERA registered
Jun 2019
Architect
PARAG URADE

Buyer community

Connect with other buyers and owners of Raje Vir Bahadur Shah Layout โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Raje Vir Bahadur Shah Layout. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.