All RERA projects
๐๏ธ
Under construction
UTTARA PARKMahaRERA P50500021619
by SUNDERSHILP BUILDERS AND DEVELOPERS
55,56,57,58,59, MOUZA HINGNA, 441110
May 2023
Possession
22.7%
Built
0
Complaints
40
Units
High risk
- Possession date passed. The proposed possession date (May 2023) has passed with construction at 22.7%.
Official RERA facts
- Registration
- P50500021619
- Status
- New
- Stage
- Certificate Signed
- Possession
- May 2023
- Construction
- 22.7% complete
- Units sold
- 40 of 40
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 23 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationnot started
Open Parkingdone
Building & registration
- RERA registered
- Jul 2019
- Floors
- 6
- Unit mix
- 40 res ยท 0 comm
- Architect
- SWAPNASHILP ARCHITECTS AND INTERIOR DESIGNER
Buyer community
Connect with other buyers and owners of UTTARA PARK โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching UTTARA PARK. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance