WHITE TIGER AND WILD FLOWERMahaRERA P50500022290

by MILINDKUMAR BHAURAO MESHRAM

148, MOUZA - SILLARI, 440015

Dec 2026
Possession
15.2%
Built
0
Complaints
168
Units
High risk
  • Possession delayed ~3 yrs. Originally promised Dec 2023, now proposed Dec 2026 per the RERA filing.
  • Behind schedule. Possession is due Dec 2026 but construction is only at 15.2%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.

Official RERA facts

Registration
P50500022290
Status
New
Stage
Certificate Signed
Possession
December 2026originally December 2023
Construction
15.2% complete
Units sold
69 of 168

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths50%
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)10%
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lighting10%
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Sept 2019
Floors
292
Unit mix
168 res ยท 0 comm
Architect
UMASHANKAR TARACHAND KADBE

Buyer community

Connect with other buyers and owners of WHITE TIGER AND WILD FLOWER โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching WHITE TIGER AND WILD FLOWER. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.