Under construction

Universal 11 up ApartmentsMahaRERA P50500022622

by UNIVERSAL HOUSE PVT. LTD.

157/427, Shivaji Nagar, 440010

Sept 2023
Possession
82.9%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Sept 2023) has passed with construction at 82.9%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Sept 2023 per the RERA filing.

Official RERA facts

Registration
P50500022622
Status
New
Stage
Certificate Signed
Possession
September 2023
Construction
82.9% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone
Open Parkingdone
Installation of Liftdone

Building & registration

RERA registered
Oct 2019
Floors
12

Buyer community

Connect with other buyers and owners of Universal 11 up Apartments โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Universal 11 up Apartments. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.