Under construction

BirchMahaRERA P50500026118

by Luxora Infrastructure Private Limited

Kh No 66 1 2 pt, Kh No 67, Kh No 56 2 pt, Mauza, 440034

Dec 2026
Possession
21.4%
Built
0
Complaints
153
Units
High risk
  • Behind schedule. Possession is due Dec 2026 but construction is only at 21.4%.
  • Promised amenities not started. Clubhouse is at 0% build with possession due Dec 2026 per the RERA filing.

Official RERA facts

Registration
P50500026118
Status
New
Stage
Certificate Signed
Possession
December 2026
Construction
21.4% complete
Units sold
49 of 153

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths48%
Water Supply39%
Sewerage (Chamber, Lines, Septic Tank , STP)50%
Storm Water Drains41%
Landscaping & Tree Planting47%
Street Lighting42%
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving station33%
Open Parkingnot started

Building & registration

RERA registered
Aug 2020
Floors
13
Unit mix
153 res ยท 0 comm
Architect
STUDIO ELEVEN

Buyer community

Connect with other buyers and owners of Birch โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Birch. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.