HIGH RISE PEARLMahaRERA P50500029223

by NEW HIGH RISE CONSTRUCTIONS

2163, SHARDA CHOWK SAKKARDARA, 440027

Sept 2023
Possession
63.6%
Built
0
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Sept 2023) has passed with construction at 63.6%.

Official RERA facts

Registration
P50500029223
Status
New
Stage
Certificate Signed
Possession
September 2023
Construction
63.6% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
May 2021
Floors
8

Buyer community

Connect with other buyers and owners of HIGH RISE PEARL โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching HIGH RISE PEARL. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.