Under construction

Kukreja Business ParkMahaRERA P50500029443

by KUKREJA INFRASTRUCTURES

plot no.- 7A, sector - 21, Non- SEZ area, MIHAN, Non SEZ area, Mihan, 441108

Mar 2029
Possession
75%
Built
0
Complaints
287
Units
High risk
  • Possession delayed ~4 yrs. Originally promised Mar 2025, now proposed Mar 2029 per the RERA filing.

Official RERA facts

Registration
P50500029443
Status
New
Stage
Certificate Signed
Possession
March 2029originally March 2025
Construction
75% complete
Units sold
0 of 287

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supply54%
Sewerage (Chamber, Lines, Septic Tank , STP)93%
Storm Water Drains86%
Water conservation /Rain water harvesting68%
Fire protection and fire safety requirements61%
Electrical meter room, sub-station, receiving station58%
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
May 2021
Floors
8
Unit mix
0 res ยท 287 comm

Buyer community

Connect with other buyers and owners of Kukreja Business Park โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Kukreja Business Park. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.