Under construction
K-SQUARE NERIUMMahaRERA P50500030653
PLOT NO 160 TO 166, 169 TO 172, CTS NO 583, SOMALWADA, 440025
Dec 2025
Possession
55%
Built
0
Complaints
42
Units
High risk
- Possession date passed. The proposed possession date (Dec 2025) has passed with construction at 55%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2025 per the RERA filing.
Official RERA facts
- Registration
- P50500030653
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2025
- Construction
- 55% complete
- Units sold
- 27 of 42
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 23 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Water Supply55%
Sewerage (Chamber, Lines, Septic Tank , STP)60%
Storm Water Drains35%
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvesting25%
Energy managemcntnot started
Fire protection and fire safety requirements15%
Electrical meter room, sub-station, receiving station35%
Building & registration
- RERA registered
- Sept 2021
- Floors
- 9
- Unit mix
- 42 res ยท 0 comm
- Architect
- ARC LOKESH KADOO
Buyer community
Connect with other buyers and owners of K-SQUARE NERIUM โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching K-SQUARE NERIUM. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.