PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

PATEL NAGARMahaRERA P50500030655

by Neelofar Mohammad Hidayatullah Anjum

189 /Part, Sadiquabad, 441111

Mar 2026
Possession
โ€”
Built
0
Complaints
13
Units
Caution
  • Possession delayed ~2 yrs. Originally promised Mar 2024, now proposed Mar 2026 per the RERA filing.

Official RERA facts

Registration
P50500030655
Status
New
Stage
Certificate Signed
Possession
March 2026originally March 2024
Construction
โ€”
Units sold
11 of 13

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths95%
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Street Lightingdone
Treatment And Disposal Of Sewage And Sullage Waterdone
Water conservation /Rain water harvestingdone
Electrical meter room, sub-station, receiving stationdone
Aggregate area of recreational Open Spacedone

Building & registration

RERA registered
Sept 2021
Architect
Dhawal Harshe Harshe

Buyer community

Connect with other buyers and owners of PATEL NAGAR โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching PATEL NAGAR. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.