KRISHNA LEELAA-3MahaRERA P50500032873

by JARRY PROFITS

PLOT NO 3 KH NO 180/6 CTS NO 391 MOUZA NARA, NARA, 440014

Jun 2027
Possession
81.6%
Built
0
Complaints
56
Units
Clean record

No delays, complaints or enforcement actions in the official disclosures we track.

Official RERA facts

Registration
P50500032873
Status
New
Stage
Certificate Signed
Possession
June 2027
Construction
81.6% complete
Units sold
50 of 56

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Planting98%
Water conservation /Rain water harvestingdone
Energy managemcntnot started
Fire protection and fire safety requirements92%
Electrical meter room, sub-station, receiving station98%
Open Parkingnot started

Building & registration

RERA registered
Feb 2022
Floors
9
Unit mix
56 res ยท 0 comm
Architect
EMANATE DESIGN LOKESH KADU

Buyer community

Connect with other buyers and owners of KRISHNA LEELAA-3 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching KRISHNA LEELAA-3. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.