Under construction

PRIME 9 APARTMENTSMahaRERA P50500034151

by SANJAY VISHWESHWARPURI BHAGWE

PLOT NO 30, SECTOR A, BUTIBORI, 441122

May 2023
Possession
40.4%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (May 2023) has passed with construction at 40.4%.

Official RERA facts

Registration
P50500034151
Status
New
Stage
Certificate Signed
Possession
May 2023
Construction
40.4% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Water conservation /Rain water harvestingdone
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving station50%

Building & registration

RERA registered
Mar 2022
Floors
5

Buyer community

Connect with other buyers and owners of PRIME 9 APARTMENTS โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching PRIME 9 APARTMENTS. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.