VISHWABHARTI RESIDENCYMahaRERA P50500035066

by BHAVESH DEORAO KUCHANWAR

1, MANEWADA, 440024

Jun 2027
Possession
43.6%
Built
0
Complaints
284
Units
High risk
  • Possession delayed ~1 yr. Originally promised Dec 2025, now proposed Jun 2027 per the RERA filing.
  • Behind schedule. Possession is due Jun 2027 but construction is only at 43.6%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2027 per the RERA filing.

Official RERA facts

Registration
P50500035066
Status
New
Stage
Certificate Signed
Possession
June 2027originally December 2025
Construction
43.6% complete
Units sold
119 of 284

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
May 2022
Floors
11
Unit mix
268 res ยท 16 comm
Architect
SANDEEP PANDIT
Public authority
NAGPUR MUNICIPAL CORPORATION

Buyer community

Connect with other buyers and owners of VISHWABHARTI RESIDENCY โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching VISHWABHARTI RESIDENCY. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.