MAHALAXMI CITY PHASE VIMahaRERA P50500045227

by DADA HOMES PRIVATE LIMITED

Kh No 56/1, 2, 3, 4, 5 & 64, Mahalaxmi City, 441111

Apr 2027
Possession
45.8%
Built
0
Complaints
0
Units
High risk
  • Behind schedule. Possession is due Apr 2027 but construction is only at 45.8%.
  • Promised amenities not started. Clubhouse is at 0% build with possession due Apr 2027 per the RERA filing.

Official RERA facts

Registration
P50500045227
Status
New
Stage
Certificate Signed
Possession
April 2027
Construction
45.8% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Planting70%
Street Lightingdone
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Water70%
Solid Waste Management And Disposal50%
Water conservation /Rain water harvesting50%
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving station50%
Aggregate area of recreational Open Space40%
Open Parkingnot started

Building & registration

RERA registered
May 2022
Floors
8

Buyer community

Connect with other buyers and owners of MAHALAXMI CITY PHASE VI โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching MAHALAXMI CITY PHASE VI. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.