PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

MAHALAXMI NAGAR 23 SECTOR 1MahaRERA P50500045779

by RAHUL JAGDISH BONDRE

178/1 PART, NAGPUR, 440025

May 2025
Possession
โ€”
Built
0
Complaints
62
Units
Caution
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due May 2025 per the RERA filing.

Official RERA facts

Registration
P50500045779
Status
New
Stage
Certificate Signed
Possession
May 2025
Construction
โ€”
Units sold
62 of 62

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths50%
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)80%
Storm Water Drainsdone
Landscaping & Tree Plantingnot started
Street Lightingnot started
Water conservation /Rain water harvesting10%

Building & registration

RERA registered
Jun 2022

Buyer community

Connect with other buyers and owners of MAHALAXMI NAGAR 23 SECTOR 1 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching MAHALAXMI NAGAR 23 SECTOR 1. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.