Under construction

ANUSAYA ASHIRWAADMahaRERA P50500046449

by VINOD DAMODHAR DEVGHARE

PLOT NO. 35, 36, KH NO. 159, NAGPUR, 441123

Nov 2026
Possession
12.3%
Built
0
Complaints
0
Units
High risk
  • Behind schedule. Possession is due Nov 2026 but construction is only at 12.3%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Nov 2026 per the RERA filing.

Official RERA facts

Registration
P50500046449
Status
New
Stage
Certificate Signed
Possession
November 2026
Construction
12.3% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supply15%
Sewerage (Chamber, Lines, Septic Tank , STP)25%
Landscaping & Tree Plantingnot started
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Water5%
Water conservation /Rain water harvesting10%
Electrical meter room, sub-station, receiving station25%
Open Parkingdone

Building & registration

RERA registered
Aug 2022
Floors
5

Buyer community

Connect with other buyers and owners of ANUSAYA ASHIRWAAD โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching ANUSAYA ASHIRWAAD. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.