๐Ÿ—๏ธ
Under construction

TATHASTUMahaRERA P50500046557

by KIRAN CONSTRUCTION

PLOT NO 20, KH NO 58/2 5823, NMC PLOT NO 410, 411, KHARE TOWN, DHARAMPETH, 440010

Jun 2027
Possession
38.8%
Built
0
Complaints
0
Units
High risk
  • Behind schedule. Possession is due Jun 2027 but construction is only at 38.8%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2027 per the RERA filing.

Official RERA facts

Registration
P50500046557
Status
New
Stage
Certificate Signed
Possession
June 2027
Construction
38.8% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)30%
Storm Water Drains30%
Landscaping & Tree Plantingnot started
Electrical meter room, sub-station, receiving stationnot started
Open Parkingnot started
Drivers Toiletnot started

Building & registration

RERA registered
Aug 2022
Floors
8

Buyer community

Connect with other buyers and owners of TATHASTU โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching TATHASTU. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.