OAK SHANTINIKETAN
CTS NO. 27, KH NO. 25/8,25/9,25/10 & 25/11, WANJRA, 440026
No delays, complaints or enforcement actions in the official disclosures we track.
Official RERA facts
- Registration
- P50500049041
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2027
- Construction
- 63.3% complete
- Units sold
- 183 of 260
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 24 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- Jan 2023
- Floors
- 14
- Unit mix
- 260 res ยท 0 comm
- Architect
- ALOK LUNIA
- Plot / CTS / survey no.
- CTS NO. 27, KH NO. 25/8,25/9,25/10 & 25/11
- Planning authority
- Maharashtra Housing and Area Development Authority (MHADA)
- Approved layout land
- 4,424.35 sq.m
- Land for this registration
- 4,424.35 sq.m
- Permissible built-up area
- 18,192 sq.m
- Registered office
- OAK Insignia
- North
- CHANDRASHEKHAR LAND
- South
- KHADAKKAR LAND
- East
- ROAD
- West
- SACHANI LAND
Project bank account
The RERA-designated account this project's payments should go to โ verify before wiring any money.
- UCO BANK โ 157335IFSC UCBA0002055MID CORPORATE BRANCH, AJANI SQUARE, NAGPUR-440003
Registered agents
- ADIVA CORPORATIONA50500005958 ยท 9823066111
Commencement Certificate documents
- BUILDING PERMIT_CC.pdf
Buyer community
Connect with other buyers and owners of OAK SHANTINIKETAN โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching OAK SHANTINIKETAN. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.