PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

KDR ROYALE

MahaRERA P50500049653Clean record

by KDR BUILDERS

CITY SURVEY NO 403 PLOT NO 2 NORTH PART KH NO 151/2, NARI, 440026

Official record
Dec 2028
Possession
80.5%
Built
0
Complaints
24
Units
Clean record

No delays, complaints or enforcement actions in the official disclosures we track.

Official RERA facts

Registration
P50500049653
Status
New
Stage
Certificate Signed
Possession
December 2028
Construction
80.5% complete
Units sold
24 of 24

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 24 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supply95%
Sewerage (Chamber, Lines, Septic Tank , STP)95%
Storm Water Drains95%
Water conservation /Rain water harvesting95%
Electrical meter room, sub-station, receiving station95%
Open Parking95%

Building & registration

RERA registered
Feb 2023
Floors
7
Unit mix
24 res ยท 0 comm
Architect
MAHESH PADOLE PADOLE
Plot / CTS / survey no.
CITY SURVEY NO 403 PLOT NO 2 NORTH PART KH NO 151/2
Planning authority
NIT
Approved layout land
665.59 sq.m
Land for this registration
665.59 sq.m
Permissible built-up area
2,047.44 sq.m
Registered office
SAKHARE NIWAS
Plot boundaries
North
ROAD
South
PLOT NO 2 SOUTH PART
East
ROAD
West
PLOT NO 3
Parking
36 two-wheeler

Project bank account

The RERA-designated account this project's payments should go to โ€” verify before wiring any money.

  • ARVIND SAHAKARI BANK LTD โ€” 2539
    IFSC ARBL0000005
    GANDHI BAUG NAGPUR

Commencement Certificate documents

  • COMMENCEMENT CERTIFICATE.pdf

Buyer community

Connect with other buyers and owners of KDR ROYALE โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching KDR ROYALE. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.