PropPin
All RERA projects
🏗️
Under construction

TECHOPS ROYALMahaRERA P50500051236

by Techops Infrastructure Pvt. Ltd.

78/1, DIGHORI, 440034

Feb 2027
Possession
71.8%
Built
0
Complaints
119
Units
Caution
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Feb 2027 per the RERA filing.

Official RERA facts

Registration
P50500051236
Status
New
Stage
Certificate Signed
Possession
February 2027originally February 2026
Construction
71.8% complete
Units sold
91 of 119

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 24 Jul 2026).

Possession extension history

  • EA17122518717Revised to February 2027

    To The Maharashtra Real Estate Regulatory Authority (MahaRERA) Subject: Explanation for Delay and Request for Extension under Section 7(3) Respected Sir/Madam, We would like to submit this explanation regarding the delay in completion of our project registered under MahaRERA, which is due to expire on 14th February 2026. The delay has occurred solely due to unforeseen natural calamities that were entirely beyond our control, and we therefore request an extension under Section 7(3) of the Real Estate (Regulation and Development) Act, 2016. The city of Nagpur, where our project is located, experienced exceptionally heavy rainfall leading to severe flooding on two major occasions — 26th July 2023 and 23rd September 2023. These unprecedented weather conditions resulted in extensive waterlogging in the project vicinity. Consequently, our project’s basement structure was completely submerged under water. Due to the flooding, it became critically unsafe to continue any civil work at the site. The presence of water posed serious structural risks, threatened the integrity of the foundation, and created hazardous working conditions for labourers and technical staff. In adherence to mandatory safety standards and to prevent any long-term structural compromise, construction activities had to be suspended immediately. Once the floodwater receded, significant time and effort were required to remove the remaining water, clear debris, and conduct essential inspections. We engaged qualified structural consultants to perform a detailed safety assessment of the affected portions, including the basement and adjoining civil works. Only after all safety checks were completed and the site was certified safe did we resume construction activities. We request that our project completion timeline be extended accordingly under the provisions of Section 7(3) of the RERA Act. We assure the Authority that we remain fully committed to completing the project at the earliest possible date, with continued adherence to all regulatory standards. We kindly request your approval for the extension in view of the above circumstances. Thanking you, Yours faithfully, For, M/S TECHOPS INFRASTRUCTURE PVT LTD Mr.Jeevan Ghime Mr. Rajendra Nakade Director and Authorised Signatory Director and Authorised Signatory Date: 10/03/2026 Place: Nagpur

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Jun 2023
Floors
41
Unit mix
100 res · 19 comm
Architect
RAVINDRA SONKUSARE
Plot / CTS / survey no.
78/1
Planning authority
NIT
Approved layout land
3,036 sq.m
Land for this registration
3,036 sq.m
Permissible built-up area
11,174 sq.m
Registered office
TECHOPS GRAND 1ST FLOOR
Plot boundaries
North
KH NO 78-1
South
9 MTR ROAD
East
9 MTR ROAD
West
KH NO 78-1
Parking
58 four-wheeler267 two-wheeler

Project bank account

The RERA-designated account this project's payments should go to — verify before wiring any money.

  • HDFC BANK — 49571
    IFSC HDFC0001248
    GR FLOOR,FIDVI TOWER ,SADAR,NAGPUR-440001

Commencement Certificate documents

  • COMMENCEMENT CERTIFICATE - NEW.pdf

Buyer community

Connect with other buyers and owners of TECHOPS ROYAL — compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet — start one and connect with the next buyer researching TECHOPS ROYAL. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.