Atharva Nagari VIIIMahaRERA P50500053130
123/2 and 123/3, Pipla, 440034
No delays, complaints or enforcement actions in the official disclosures we track.
Official RERA facts
- Registration
- P50500053130
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2028
- Construction
- 76.8% complete
- Units sold
- 151 of 210
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 24 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- Oct 2023
- Floors
- 15
- Unit mix
- 210 res ยท 0 comm
- Plot / CTS / survey no.
- 123/2 and 123/3
- Planning authority
- CHANDRAKANT BABURAO SURAMWAR
- Approved layout land
- 16,200 sq.m
- Land for this registration
- 16,200 sq.m
- Recreational open space
- 1,510.54 sq.m
- Permissible built-up area
- 48,151.26 sq.m
- Registered office
- SHUBHAM TOWER
- North
- Khasra Number 152
- South
- Khasara Number 123 by 1
- East
- Khasara Number 123 by 1
- West
- Khasara Number 151
Project bank account
The RERA-designated account this project's payments should go to โ verify before wiring any money.
- BANK OF BARODA โ 3503IFSC BARB0AMBAZASOUTH AMBAZA BRANCH,K-5,MANJULA BLDG.,8 RASTHA CHOWK LAXMINAGAR,NAGPUR,440022
Commencement Certificate documents
- BUILDING PERMITT_compressed.pdf
- Ec atharva 8.pdf
- BLDG PERMIT.pdf
Buyer community
Connect with other buyers and owners of Atharva Nagari VIII โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching Atharva Nagari VIII. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.