Ibrahim Residency
Plot No 5, KH No 95/2,95/3,95/4,95/5,95/6,95/7,95/8 Mouze Gorewada, Mouze Gorewada, 440001
No delays, complaints or enforcement actions in the official disclosures we track.
Official RERA facts
- Registration
- P50500053487
- Status
- New
- Stage
- Certificate Signed
- Possession
- August 2027
- Construction
- 59.1% complete
- Units sold
- 26 of 40
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 24 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- Nov 2023
- Floors
- 5
- Unit mix
- 40 res ยท 0 comm
- Architect
- C D GIRIPUNJE
- Plot / CTS / survey no.
- Plot No 5, KH No 95/2,95/3,95/4,95/5,95/6,95/7,95/8 Mouze Gorewada
- Planning authority
- NIT NAGPUR
- Approved layout land
- 1,484.64 sq.m
- Land for this registration
- 1,484.64 sq.m
- Permissible built-up area
- 3,576.93 sq.m
- Promoter contact
- Mohammed Fahim Ibrahim
- Registered office
- Farm House
- North
- Road
- South
- Plot No 14
- East
- Plot No 6
- West
- Babbu Hotel Farm
Project bank account
The RERA-designated account this project's payments should go to โ verify before wiring any money.
- CANARA BANK โ 30184IFSC CNRB0001488Sadar Bazar
Commencement Certificate documents
- Commencement Certificate.pdf
Buyer community
Connect with other buyers and owners of Ibrahim Residency โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching Ibrahim Residency. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.