Under construction

GURUKRIPAMahaRERA P50500078365

by SHREE RENUKA INFRA LLP

PLOT NO 5, CTS NO 280, KH NO 102/3, Patwari Halka No 8A, Sheet No 112/82, GOREWADA, 440013

Sept 2027
Possession
72.2%
Built
0
Complaints
17
Units
High risk
  • Mortgaged to a lender. MahaRERA's financial encumbrance declaration shows this project is mortgaged to a lender โ€” a lender's claim can outrank a buyer's if the promoter defaults.
  • Possession delayed ~2 yrs. Originally promised Mar 2026, now proposed Sept 2027 per the RERA filing.

Official RERA facts

Registration
P50500078365
Status
New
Stage
Certificate Signed
Possession
September 2027originally March 2026
Construction
72.2% complete
Units sold
1 of 17

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 24 Jul 2026).

Mortgaged to a lender

MahaRERA's financial encumbrance declaration shows this project is mortgaged to a lender. If the promoter defaults, the lender's claim can outrank a buyer's โ€” worth raising with the builder before booking.

Landowner

Mr SANJAY RAGHURAJ TIWARI, GOURI ATKAR, DILIP ATKAR

Possession extension history

  • EA04042620556Revised to September 2027

    To The Maharashtra Real Estate Regulatory Authority (MahaRERA) Subject: Reason for Extension of Project โ€“ GURUKRIPA Bearing RERA No. P50500078365 Respected Sir/Madam, The project is delayed primarily due to non-issuance of Occupation Certificate (OC) by the competent authority despite substantial completion of works. Additionally, the project is further delayed pending approval from Nagpur Improvement Trust (NIT) for our proposal to construct two more floors over the existing floors; the acknowledgment receipt for this NIT permission application is enclosed herewith. These external delays, beyond our control, necessitate extension to protect allottee interests. We confirm full compliance: All Quarterly Progress Reports (QPRs) and Annual Progress Reports (APRs) up to date have been submitted via the MahaRERA portal. No complaints or violations are pending. Thank you for your time and cooperation. For, M/s Shree Renuka Infra LLP Mr. Dilip Dattatray Atkar (Partner & Authorized Signatory)

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supply90%
Sewerage (Chamber, Lines, Septic Tank , STP)85%
Storm Water Drains90%
Water conservation /Rain water harvesting90%
Energy managemcnt85%
Fire protection and fire safety requirements90%
Electrical meter room, sub-station, receiving station95%
Open Parking90%

Building & registration

RERA registered
Dec 2024
Floors
5
Unit mix
13 res ยท 4 comm
Architect
VIKAS PADOLE
Plot / CTS / survey no.
PLOT NO 5, CTS NO 280, KH NO 102/3, Patwari Halka No 8A, Sheet No 112/82
Planning authority
NAGPUR IMPROVEMENT TRUST
Approved layout land
1,071 sq.m
Land for this registration
1,071 sq.m
Recreational open space
0 sq.m
Permissible built-up area
3,571.65 sq.m
Registered office
ARYA HOMES,PLOT NO 87
Plot boundaries
North
36 MTRS WIDE ROAD
South
LAYOUT BOUNDARY
East
PLOT NO 4
West
LAYOUT BOUNDARY
Parking
20 four-wheeler24 two-wheeler

Project bank account

The RERA-designated account this project's payments should go to โ€” verify before wiring any money.

  • YES BANK โ€” 168353
    IFSC YESB0001376
    GROUND FLOOR, PLOT NO.193, DR. AGRAWAL BUILDING,MEDICAL SQUARE, NAGPUR- 440 009

Commencement Certificate documents

  • VERIFICATION OF OC CC.pdf
  • NIT PERMIT comencement certificate.pdf

Buyer community

Connect with other buyers and owners of GURUKRIPA โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching GURUKRIPA. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.